2.               AIR QUALITY

Monitoring Requirements

 

2.1              According to EM&A Manual of the Kai Tak Development EIA Study and contract requirement under Contract No. KLN/2010/04, 1-hour and 24-hour TSP monitoring were conducted to monitor the air quality for KTD. For regular impact monitoring, a sampling frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six days shall be undertaken when the highest dust impact occurs. Appendix A shows the established Action/Limit Levels for the environmental monitoring works.

Monitoring Locations

 

2.2              Six designated monitoring stations were selected for air quality monitoring programme. Impact dust monitoring was conducted at five air quality monitoring stations, namely Kai Tak Operational Base (AM1(A)), Lee Kau Yan Memorial School (AM2), Holy Trinity Bradbury Centre (AM3(A)), EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling College (AM5(A)) in the reporting month.  Table 2.1 describes the air quality monitoring locations, which are also depicted in Figure 2.

 

Table 2.1    Locations for Air Quality Monitoring

Monitoring Stations

Locations

Location of Measurement

AM1(A)

Kai Tak Operational Base

Rooftop (about 9/F) Area

AM2

Lee Kau Yan Memorial School

Rooftop (about 8/F) Area

AM3(A)   

Holy Trinity Bradbury Centre 

Rooftop (about 8/F) Area

AM4(A)  

EMSD Workshops

Rooftop  (about 6/F)  Area

AM5(A)

Po Leung Kuk Ngan Po Ling College

Rooftop  (about 10/F)  Area

#AM6

PA 15

Site 1B4 (Planned)


Remarks: # Baseline/Impact monitoring will be conducted when the premise is occupied or instructed by Engineer.

Monitoring Equipment

 

2.3              Table 2.2 summarizes the equipment used in the impact air monitoring programme. Copies of calibration certificates are attached in Appendix B.

 

Table 2.2    Air Quality Monitoring Equipment

Equipment

Model and Make

Quantity

Calibrator

G25A

1

1-hour TSP Dust Meter

Laser Dust Monitor ¡V Model LD3B

4

HVS Sampler

GMWS 2310 c/w of TSP sampling inlet

5

Wind Anemometer

Davis Weather Monitor II, Model no. 7440

1

Monitoring Parameters, Frequency and Duration

 

2.4              Table 2.3 summarizes the monitoring parameters and frequencies of impact dust monitoring for the whole construction period.  The air quality monitoring schedule for the reporting month is shown in Appendix D.

 

Table 2.3    Impact Dust Monitoring Parameters, Frequency and Duration

Parameters

Frequency

1-hr TSP

Three times / 6 days

24-hr TSP

Once / 6 days

Monitoring Methodology and QA/QC Procedure

1-hour TSP Monitoring

Measuring Procedures

 

2.5              The measuring procedures of the 1-hour dust meters were in accordance with the Manufacturer¡¦s Instruction Manual as follows:

¡P          The 1-hour dust meter is placed at least 1.3 meters above ground.

¡P          Set POWER to ¡§ON¡¨ and make sure that the battery level was not flash or in low level.

¡P          Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet has been released.

¡P          Push the knob at MEASURE position.

¡P          Set time/mode setting to [BG] by pushing the time setting switch.  Then, start the background measurement by pushing the start/stop switch once.  It will take 6 sec. to complete the background measurement.

¡P          Push the time setting switch to change the time setting display to [MANUAL] at the bottom left of the liquid crystal display.  Finally, push the start/stop switch to stop the measuring after 1 hour sampling.

¡P          Information such as sampling date, time, count value and site condition were recorded during the monitoring period.

 

Maintenance/Calibration

 

2.6              The following maintenance/calibration was required for the direct dust meters:

¡P      Check and calibrate the meter by HVS to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.

 

24-hour TSP Monitoring

       

Instrumentation

 

2.7              High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate sampling inlets were employed for 24-hour TSP monitoring.  The sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complied with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50). Moreover, the HVS also met all the requirements in section 2.5 of the updated EM&A Manual.

 

Operating/Analytical Procedures

 

2.8              Operating/analytical procedures for the operation of HVS were as follows:

 

¡P          A horizontal platform was provided with appropriate support to secure the samplers against gusty wind.

¡P          No two samplers were placed less than 2 meters apart.

¡P          The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.

¡P          A minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samples.

¡P          A minimum of 2 meters separation from any supporting structure, measured horizontally was required.

¡P          No furnaces or incineration flues were nearby.

¡P          Airflow around the sampler was unrestricted.

¡P          The sampler was more than 20 meters from the drip line.

¡P          Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

 

2.9              Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3/min. and 1.4 m3/min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50.

 

2.10          For TSP sampling, fiberglass filters have a collection efficiency of > 99% for particles of 0.3 £gm diameter were used.

 

2.11          The power supply was checked to ensure the sampler worked properly.  On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station.

 

2.12          The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen.

 

2.13          The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.  Then the filter holding frame was tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges.

 

2.14          The shelter lid was closed and secured with the aluminum strip.

 

2.15          The timer was then programmed.  Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number).

 

2.16          After sampling, the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd.) for weighing.  The elapsed time was also recorded.

 

2.17          Before weighing, all filters were equilibrated in a conditioning environment for 24 hours.  The conditioning environment temperature should be between 25¢XC and 30¢XC and not vary by more than ¡Ó3¢XC; the relative humidity (RH) should be < 50% and not vary by more than ¡Ó5%. A convenient working RH is 40%.

 

Maintenance/Calibration

 

2.18          The following maintenance/calibration was required for the HVS:

 

¡P          The high volume motors and their accessories were properly maintained.  Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working condition.

¡P          High volume samplers were calibrated at bi-monthly intervals using G25A Calibration Kit throughout all stages of the air quality monitoring.

Results and Observations

 

2.19          All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

2.20          All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

2.21          The air temperature, precipitation and the relative humidity data was obtained from Hong Kong Observatory where the wind speed and wind direction were recorded by the installed Wind Anemometer set at rooftop (about 9/F) of Kai Tak Operational Base. The location is shown in Figure 4.  These weather information for the reporting month is summarized in Appendix C.

 

2.22          The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring results are shown in Appendices E and F respectively.   

 

2.23          The summary of exceedance record in reporting month is shown in Appendix H.  No exceedance was recorded for the air quality monitoring.

 

2.24          According to our field observations, the major dust source identified at the designated air quality monitoring stations are as follows:

Station

Major Dust Source

AM1(A) ¡V  Kai Tak Operational Base

Road Traffic Dust

Exposed site area

Site vehicle movement

 

AM2 ¡V   Lee Kau Yan Memorial School

AM3(A) -  Holy Trinity Bradbury Centre

Road Traffic Dust

Site vehicle movement

AM4(A) ¡V EMSD Workshops

Sand Depot

Concrete Batching Plant

AM5(A)  ¡V   Po Leung Kuk Ngan Po Ling College

Road Traffic Dust

Loading/unloading activities