1.1 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It covers a land area of about 328 hectares. The Project also covers Kowloon Bay and Kwun Tong Typhoon Shelter and the adjacent water bodies. The general layout of the Project is shown in Figure 1.
1.2 Civil Engineering and Development Department (CEDD) had completed an Environmental Impact Assessment (EIA) study for KTD under Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction (hereafter called “Schedule 3 EIA Report”). The Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance (EIAO) in March 2009.
1.3 As recommended in the Schedule 3 EIA Report, EM&A programme shall be required for different phases of the KTD as a whole. In August 2010, Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD. Under the Contract, Environmental Team (ET(KTD)) shall oversee all the environmental issues within the Kai Tak Development (KTD), including but not limit to the Schedule 2 Designated Projects and other work contracts.
1.4 The Contract KLN/2010/04 was superseded by Contract No. KLN/2013/16 on 12 February 2014. EM&A Works for Kai Tak Development shall continue and reported under the new Contract.
1.5
Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring
and Audit (EM&A) works for KTD Contract No. KLN/2013/16. This is the 4th Monthly EM&A report summarizing the
EM&A works for the Project in June 2014.
1.6 Different parties with different levels of involvement in the project organization include:
·
Environmental Protection Department (The
Authority)
·
Project
Proponent – Civil Engineering and
Development Department (CEDD)
·
The
Engineer and the Engineer’s Representative (ER) – Black & Veatch (BV)
·
Environmental
Team (ET(KTD)) – Cinotech Consultants Limited (CCL)
·
Independent
Environmental Checker (IEC(KTD))
– Mott MacDonald Hong Kong Limited (MMHK)
1.7 The key contacts of the Project are shown in Table 1.1.
Table
1.1 Key
Project Contacts
|
Role |
Contact Person |
Phone No. |
Fax No. |
|
|
CEDD |
Project
Proponent |
Mr. K Y SHIN |
2301 1461 |
2301 1277 |
|
Mr. Colin IP |
3104 2197 |
2301 1277 |
||
|
BV |
Engineer’s Representative |
Ms. Esther TONG |
2608 7379 |
2601 3988 |
|
Cinotech |
Environmental
Team (KTD) |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
|
Ms. Ivy Tam |
2151 2090 |
|||
|
Mott MacDonald |
Independent
Environmental Checker (KTD) |
Mr. Terence Kong |
2828 5919 |
2827 1823 |
1.8 There are several works contracts undertaken within KTD during the reporting month. In order to collect relevant environmental information from the work contracts and incorporate into this monthly monitoring report, a survey form for monthly environmental performance records was sent to all work contracts/tenants within KTD on 30 June 2014. The survey form shall be returned by 5th each month to provide the environmental monthly information of respective work contracts within KTD.
1.9 Based on the returned survey form from work contracts and site observation for short term tenancy (STT) / temporary government land allocation (TGLA) during the weekly site inspection, the major site activities undertaken within Kai Tak Development (KTD) in the reporting month are summarized in Table 1.2:
Table 1.2 Summary Table
for Major Site Activities undertaken within KTD
in the Reporting month
KDO, CEDD projects
|
Contract No. |
Project Title |
Site Activities |
|
CV/2013/02 |
Maintenance Contract for Seawall and Navigation Channels (2013-2016) - Dredging at Kai Tak Cruise Terminal Stage 2 |
1) Dredge and
disposal of marine sediment 2) Impact water
monitoring 3) Interim Survey |
|
KL/2010/02 |
Kai Tak
Development – Kai Tak Approach Channel and Kwun Tong Typhoon Shelter Improvement Works (Phase 1) |
1) Full scale bioremediation 2) Water quality monitoring for bioremediation 3) Sediment sampling |
|
KL/2010/03 |
Kai
Tak Development Stage 2 Infrastructure Works at
North Apron Area |
1) Site clearance 2) Road works 3) Road drainage construction 4) Box culvert construction 5) Sewage pumping station construction |
|
KL/2011/01 |
Kai Tak Development –Reconstruction
and Upgrading of Kai Tak Nullah |
1) Excavation for construction of box culverts 2) ELS for construction of box culvert 3) Rebar fixing and concreting for construction of
box culvert 4) TTA at Kai Fuk Road 5) Settlement monitoring 6) Drainage diversion works at downstream 7) Rebar fixing and concreting for construction of
open channel 8) Construction of temporary steel decking for TTA
near Kai Fuk Road |
|
KL/2012/02 |
Kai Tak Development -
Stage 3A Infrastructure at Former North Apron Area |
1) Site clearance 2) General road works 3) Road drainage construction 4) Underpass construction 5) Subway construction |
|
KL/2012/03 |
Kai
Tak Development Stage 4 Infrastructure at Former North
Apron Area |
1) Preparation works for base slab construction of
Pumping Station PS2 2) Excavation and structural works for box culvert
B5 3) Construction of sewerage works at Road D2 4) Road widening works at Sung Wong Toi Road 5) Excavation of pits for pipe jacking works at TKW
area 6) Fabrication of first batch of Box Culvert B6
precast unit 7) Excavation and lateral support works for pumping
station NPS |
DSD projects
|
Contract No. |
Project Title |
Site Activities |
|
DC/2010/03 |
Kai Tak Nullah Improvement Works at Prince Edward Road East |
1) Maintain Engineer's Principal Office 2) Maintain Contractor's Site Office and Site Compound 3) Stockpile excavated C&D waste material of Prince Edward Road East |
|
DC/2011/04 |
Reconstruction, Improvement and
Rehabilitation of Kai Tak River from Wong Tai Sin
Police Station to Tung Tau |
1) Maintain of the access road, Engineer’s Principal Office and Contractor’s
Site Office |
WSD projects
|
Contract No. |
Project Title |
Site Activities |
|
3/WSD/08 |
Replacement and Rehabilitation of
Water Mains Stages 2 & 3 |
1) Storage
of water works material |
|
6/WSD/08 |
1) Construction
material storage (Portion 2-3) |
|
|
7/WSD/08 |
1) Site
Office of the Contractor 2) Storage
of water works material 3) Storage
and sorting of C&D materials |
|
|
8/WSD/08 |
1) Pipe
materials storage (Kai Tak - Portion 1-2) |
ArchSD projects
|
Contract No. |
Project Title |
Site Activities |
|
SS A501 |
Design and Construction of Centre of
Excellence in Paediatrics |
1) Sheet Pilling 2) Pilling Works |
|
SS B507 |
Construction of Two 30-classroom Primary
Schools at Site 1A-3 and Site 1A-4, Kai Tak
Development |
1) Site clearance and establishment 2) Excavation and lateral support 3) Percussive piling 4) Construction of site office |
|
SS W304 |
Design and Construction
of Trade and Industry Tower in Kai Tak Development
Area |
1) Rebar fixing 2) Formwork and falsework 3) Concreting 4) Drainage Works 5) Block wall construction 6) Curtain wall installation |
CLP projects
|
Contract No. |
Project Title |
Site Activities |
|
|
CLP Kai Tak Cable Tunnel |
1) Miscellaneous works 2) Welding steel members 3) ELS works 4) Drilling hole for grouting curtain 5) Sheet pile works |
|
CLP Cabling Work in Kai Tak Area |
132/11kV & LV Cable Installation |
1) 11kV & LV cable laying and jointing |
EMSD projects
|
Contract No. |
Project Title |
Site Activities |
|
1017EM10 |
Design-Build-Operate
a District Cooling System (Phase II Works) at Kai Tak
Development |
1) E&M installation for Cooling Plant and T&C 2) Dewatering at SDCS Plants and SWPR 3) ELS works and Construction of Outfall 4) Operation of temporary District Cooling Plant at SDCS 5) ELS & DCS Pipeworks installation at Cargo
Circuit 6) Backfilling and reinstatement of existing seawall at Intake 7) Backfilling at SDCS |
|
1020EM12A |
District Cooling
System (DCS) at Kai Tak Development (KTD) Phase III
(Package A)-Chilled Water Pipe Laying Works |
No information was provided from the Contractor. |
MTR projects
|
Contract No. |
Project Title |
Site Activities |
|
1107 |
Diamond Hill to Kai Tak
Tunnels |
1) Site investigation works 2) Investigation and removal of old foundation works 3) Sheet piling works 4) Shaft excavation 5) Site preparation works 6) Grouting works |
|
1108 |
Kai Tak Station and Associated Tunnels |
1)
Excavation and shotcreting on excavated
slope 2)
Breaking of existing underground boulder 3)
Disposal of marine deposit 4)
Station structure: track slab concreting, rebar fixing, formwork
erection 5)
SCL1107/1108 interface stub tunnel ELS 6)
Mined tunnel: jet grouting; sheet piling for water cut off wall by
silent pile 7)
Base lab construction |
|
1108A |
Kai
Tak Barging Point Facilities |
1) Spoil Disposal 2) Watering of Site 3) Vehicular Gate Installation |
|
1109 |
Shatin to Central
Link: Ma Tau Wai and To Kwa
Wan Stations and Tunnels |
1)
TAM
Grouting 2)
Archaeological
Survey 3)
Socketted H Piling 4)
Proof-drilling 5)
Bulk
Excavation 6)
Traffic
Diversion 7)
Strut
Installation 8)
Sheet
Piling 9)
TBM
Set up works |
HKHA projects
|
Contract No. |
Project Title |
Site Activities |
|
20130225 |
Foundation for Public Rental Housing Development
at Ex-Kwai Chung Police Married Quarters (Kai Tak 1G1(B) Site) |
No information was provided from the Contractor. |
URA projects
|
Contract No. |
Project Title |
Site Activities |
|
New Kowloon Inland Lot No. 6515 |
Kai Tak Flat-For-Flat Development |
1) Environmental monitoring works 2) H1 construction of typical floor 10/F~14/F 3) H2 construction of typical floor 10/F~14/F 4) H3 construction of typical floor 10/F~14/F 5) L1 construction of typical floor 4/F~R/F 6) Retail block – concreting to footing 7) E&M installation 8) Brown area – installation of ELS works for manhole |
COHL projects
|
Contract No. |
Project Title |
Site Activities |
|
New Kowloon Inland Lot No. 6516 & 6517 |
New Kowloon Inland Lot No. 6516 & 6517 -
Proposed Residential Development |
No information was provided from the Contractor. |
List of Temporary
Government Land Allocations (TGLAs)
|
TGLA No. |
Name of
Occupants |
Site Activities |
|
GLA-TNK 1591 |
CE/LW, Civil Engineering & Development Department |
Works area |
|
GLA-TNK 1751 |
Housing Department |
Works Area and Storage Area |
|
GLA-TNK 1801 |
Housing Department |
Works and storage area (Site 1B3) |
|
GLA-TNK 1177 |
Electrical and Mechanical Services Department |
Vehicle maintenance depot next to the existing
HATCL II Building |
|
GLA-TNK 1338 |
Highways Department |
Maintenance Depot; off Cargo Circuit |
|
GLA-TNK 1635 |
CE/SP, Drainage Services Department |
Works Area |
|
GLA-TNK 1713 |
CHE/K, Highways Department |
Storage |
|
GLA-TNK 1749 |
CE/SP, Drainage Services Department |
Additional Works
area |
|
GLA-TNK 1568 |
Fire Services Department |
Driving training ground |
|
GLA-TNK 1360 |
HK Police Force |
Storage of police water barriers and metal gates |
|
GLA-TNK 1675 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1760 |
CE/DP, Drainage Services Department |
Site office and storage area |
|
GLA-TNK 1646 |
CGE/LPM, Civil Engineering and Development Department |
Stockpiling of excavated & construction materials |
|
GLA-TNK 1608 |
Transport Department |
Works Area |
|
GLA-TNK 1580 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1581 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1334 |
CE/Construction, Water Supplies Department |
Works Area |
|
GLA-TNK 1144 |
CE/PW, Civil Engineering and Development Department |
Works Area |
|
GLA-TNK 1226 |
||
|
GLA-TNK 1191 |
Hong Kong Observatory |
Automatic Weather station |
|
GLA-TNK 1542 |
Weather Station |
|
|
GLA-TNK 1507 |
CE/SD, Civil Engineering and Development Department |
Barging point and storage area |
|
GLA-TNK 1671 |
Civil Engineering and Development Department |
Works Area/Engineer’s & Contractor’s
Accommodation/Fabrication Yard |
|
GLA-TNK 1707 |
PM(K), Civil Engineering & Development Department |
Works Area/Stockpiling Area |
|
GLA-TNK 1759 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1823 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1850 |
PM(K), Civil Engineering & Development Department |
Works Area |
|
GLA-TNK 1548 |
CE/PM, Water Supplies Department |
Works Area |
|
GLA-TNK 1571 |
ArchSD |
Works Area |
|
GLA-TNK 1692 |
CE/CM, Drainage Supplies Department |
Works Area |
|
GLA-TNK 1693 |
Architectural Services Department |
Works Area/Stockpiling area |
|
GLA-TNK 1899 |
CE/K, Water Supplies Department |
Works Area |
|
GLA-TNK 1717 |
EMSD |
Works Area/Stockpiling Area/Site Office for DCS |
|
GLA-TNK 1814 |
CMP 202, Architectural Services Department |
Works Area |
|
GLA-TNK 1821 |
CE/Municipal, EMSD |
Works/Storage Area |
|
GLA-TNK 1862 |
CE/PM, DSD |
Works Area |
|
GLA-TNK 1885 |
ArchSD |
Barging Point |
List of Short Term Tenancy
(STT)
|
STT No. |
Name of
Occupants |
Site Activities |
|
KX2688 |
Goldway Parking Ltd. |
Car-park |
|
KX2345 |
CLP Power Hong Kong Limited |
Storage of construction materials and plant
equipment |
|
KX2662 |
Hong Kong Cricket Association |
Operation of Hong Kong Cricket Association |
|
KX2628 |
Moral Well International Enterprise Limited |
Car-park |
|
KX2552 |
Era International Investment Limited |
Car-park |
|
KX2629 |
Graceful Ocean Development Limited |
Car-park |
|
KX2261 |
Hong Kong Aviation Club
Ltd. |
Training for air traffic controllers |
|
KX2574 |
Future Chinese Limited |
Car-park |
|
KX2575 |
Nanjing Limited |
Car-park |
|
KX2109 |
Multi-Light Limited |
1) Concrete production 2) Storage of building materials |
|
KX2675 |
Wang Lee Building Materials Trading Ltd. |
Operation of business in the recovery and
recycling |
|
KX2676 |
Ga Shing Transport Co. |
Operation of business in the recovery and
recycling |
|
KX2677 |
Chuen Kee Metal Trading Co Ltd. |
Operation of business in the recovery and
recycling |
|
KX2678 |
Kin Xun Environment Recycle Ltd |
Operation of business in the recovery and
recycling |
|
KX2569 |
Sureguard Logistics Limited |
Open storage of goods and dangerous goods |
|
KX2641 |
Citybus Limited |
Parking of buses |
|
KX2642 |
Goldway Parking Ltd. |
Car-park |
|
KX2189 |
The Hong Kong Housing Authority |
Site and road formation, building and associated
works for the development of the premises |
|
KX2190 |
||
|
KX2616 |
CLP Power Hong Kong Limited |
Constructing, maintaining and operating
Underground Strata I and II and
The Pink Edged Red Area |
1.10 The construction programme showing the inter-relationship with environmental protection/mitigation measures are presented in Table 1.3.
Table
1.3
Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures
|
Construction
Works |
Major
Environmental Impact |
Control
Measures |
|
As mentioned in Table 1.2 |
Noise, dust impact, water
quality and waste generation |
Sufficient watering of the works site with active dust emitting
activities
Properly cover the stockpiles
On-site waste sorting and implementation of trip ticket system
Appropriate desilting/sedimentation devices
provided on site for treatment before discharge
Use of quiet plant and well-maintained construction plant
Provide movable noise barrier
Provide sufficient mitigation measures as recommended in Approved EIA
Report/Lease requirement
Provide silt curtain for dredging and filling activities |
1.11 The EM&A programme requires construction noise monitoring, air quality monitoring, landscape and visual monitoring and environmental site audit. The EM&A requirements for each parameter are described in the following sections, including:
· All monitoring parameters;
· Action and Limit levels for all environmental parameters;
· Event Action Plans;
· Environmental mitigation measures, as recommended in the Schedule 3 EIA Report; and
· Environmental requirements in contract documents under Contract No. KLN/2013/16.
1.12 The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 6 of this report.
1.13
This report presents the
monitoring results, observations, locations, equipment, period, methodology and
QA/QC procedures of the required monitoring parameters, namely air quality and
noise levels and audit works for the Project in June 2014.