1.              INTRODUCTION

Background

 

1.1              The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It covers a land area of about 328 hectares. The Project also covers Kowloon Bay and Kwun Tong Typhoon Shelter and the adjacent water bodies. The general layout of the Project is shown in Figure 1.

 

1.2              Civil Engineering and Development Department (CEDD) had completed an Environmental Impact Assessment (EIA) study for KTD under Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction (hereafter called “Schedule 3 EIA Report”). The Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance (EIAO) in March 2009.

 

1.3              As recommended in the Schedule 3 EIA Report, EM&A programme shall be required for different phases of the KTD as a whole. In August 2010, Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD.  Under the Contract, Environmental Team (ET(KTD)) shall oversee all the environmental issues within the Kai Tak Development (KTD), including but not limit to the Schedule 2 Designated Projects and other work contracts.

 

1.4              The Contract KLN/2010/04 was superseded by Contract No. KLN/2013/16 on 12 February 2014.  EM&A Works for Kai Tak Development shall continue and reported under the new Contract.

 

1.5              Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD Contract No. KLN/2013/16.  This is the 4th Monthly EM&A report summarizing the EM&A works for the Project in June 2014.

 

Project Organizations

 

1.6              Different parties with different levels of involvement in the project organization include:

·          Environmental Protection Department (The Authority)

·          Project Proponent – Civil Engineering and Development Department (CEDD)

·          The Engineer and the Engineer’s Representative (ER) – Black & Veatch (BV)

·          Environmental Team (ET(KTD)) – Cinotech Consultants Limited (CCL)

·          Independent Environmental Checker (IEC(KTD)) – Mott MacDonald Hong Kong Limited (MMHK)


1.7              The key contacts of the Project are shown in Table 1.1.

 

Table 1.1          Key Project Contacts

            Party

Role

Contact Person

Phone No.

Fax No.

CEDD

Project Proponent

Mr. K Y SHIN

2301 1461

2301 1277

Mr. Colin IP

3104 2197

2301 1277

BV

Engineer’s  Representative

Ms. Esther TONG

2608 7379

2601 3988

Cinotech

Environmental Team (KTD)

Dr. Priscilla Choy

2151 2089

3107 1388

Ms. Ivy Tam

2151 2090

Mott MacDonald

Independent Environmental Checker (KTD)

Mr. Terence Kong

2828 5919

2827 1823

Construction Activities undertaken during the Reporting Month

 

1.8              There are several works contracts undertaken within KTD during the reporting month.  In order to collect relevant environmental information from the work contracts and incorporate into this monthly monitoring report, a survey form for monthly environmental performance records was sent to all work contracts/tenants within KTD on 30 June 2014. The survey form shall be returned by 5th each month to provide the environmental monthly information of respective work contracts within KTD.

 

1.9              Based on the returned survey form from work contracts and site observation for short term tenancy (STT) / temporary government land allocation (TGLA)  during the weekly site inspection, the major site activities undertaken within Kai Tak Development (KTD) in the reporting month are summarized in Table 1.2:

 

Table 1.2      Summary Table for Major Site Activities undertaken within KTD in the Reporting month

 

KDO, CEDD projects

Contract No.

Project Title

Site Activities

CV/2013/02

Maintenance Contract for Seawall and Navigation Channels (2013-2016) - Dredging at Kai Tak Cruise Terminal Stage 2

1)    Dredge and disposal of marine sediment

2)    Impact water monitoring

3)    Interim Survey

 

KL/2010/02

Kai Tak Development – Kai Tak Approach Channel and Kwun Tong Typhoon Shelter Improvement Works (Phase 1)

1)    Full scale bioremediation

2)    Water quality monitoring for bioremediation

3)    Sediment sampling

KL/2010/03

Kai Tak Development Stage 2 Infrastructure Works at North Apron Area

1)    Site clearance

2)    Road works

3)    Road drainage construction

4)    Box culvert construction

5)    Sewage pumping station construction

KL/2011/01

Kai Tak Development –Reconstruction and Upgrading of Kai Tak Nullah

1)    Excavation for construction of box culverts

2)    ELS for construction of box culvert

3)    Rebar fixing and concreting for construction of box culvert

4)    TTA at Kai Fuk Road

5)    Settlement monitoring

6)    Drainage diversion works at downstream

7)    Rebar fixing and concreting for construction of open channel

8)    Construction of temporary steel decking for TTA near Kai Fuk Road

KL/2012/02

Kai Tak Development - Stage 3A Infrastructure at Former North Apron Area

1)    Site clearance

2)    General road works

3)    Road drainage construction

4)    Underpass construction

5)    Subway construction

KL/2012/03

Kai Tak Development Stage 4 Infrastructure at Former North Apron Area

1)    Preparation works for base slab construction of Pumping Station PS2

2)    Excavation and structural works for box culvert B5

3)    Construction of sewerage works at Road D2

4)    Road widening works at Sung Wong Toi Road

5)    Excavation of pits for pipe jacking works at TKW area

6)    Fabrication of first batch of Box Culvert B6 precast unit

7)    Excavation and lateral support works for pumping station NPS

 

DSD projects

Contract No.

Project Title

Site Activities

DC/2010/03

 

Kai Tak Nullah Improvement Works at Prince Edward Road East

1)    Maintain Engineer's Principal Office

2)    Maintain Contractor's Site Office and Site Compound

3)    Stockpile excavated C&D waste material of Prince Edward Road East

DC/2011/04

Reconstruction, Improvement and Rehabilitation of Kai Tak River from Wong Tai Sin Police Station to Tung Tau

1)    Maintain of the access road, Engineer’s Principal Office and Contractor’s Site Office

 

WSD projects

Contract No.

Project Title

Site Activities

3/WSD/08

Replacement and Rehabilitation of Water Mains Stages 2 & 3

1)    Storage of water works material

6/WSD/08

1)    Construction material storage (Portion 2-3)

7/WSD/08

1)    Site Office of the Contractor

2)    Storage of water works material

3)    Storage and sorting of C&D materials

8/WSD/08

1)    Pipe materials storage (Kai Tak - Portion 1-2)

ArchSD projects

Contract No.

Project Title

Site Activities

SS A501

Design and Construction of Centre of Excellence in Paediatrics

1)    Sheet Pilling

2)    Pilling Works

SS B507

Construction of Two 30-classroom Primary Schools at Site 1A-3 and Site 1A-4, Kai Tak Development

1)    Site clearance and establishment

2)    Excavation and lateral support

3)    Percussive piling

4)    Construction of site office

SS W304

Design and Construction of Trade and Industry Tower in Kai Tak Development Area

1)    Rebar fixing

2)    Formwork and falsework

3)    Concreting

4)    Drainage Works

5)    Block wall construction

6)    Curtain wall installation

 

CLP projects

Contract No.

Project Title

Site Activities

 

CLP Kai Tak Cable Tunnel

1)    Miscellaneous works

2)    Welding steel members

3)    ELS works

4)    Drilling hole for grouting curtain

5)    Sheet pile works

CLP Cabling Work in Kai Tak Area

132/11kV & LV Cable Installation

1)    11kV & LV cable laying and jointing

 

EMSD projects

Contract No.

Project Title

Site Activities

1017EM10

Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak Development

1)    E&M installation for Cooling Plant and T&C

2)    Dewatering at SDCS Plants and SWPR

3)    ELS works and Construction of Outfall

4)    Operation of temporary District Cooling Plant at SDCS

5)    ELS & DCS Pipeworks installation at Cargo Circuit

6)    Backfilling and reinstatement of existing seawall at Intake

7)    Backfilling at SDCS

1020EM12A

District Cooling System (DCS) at Kai Tak Development (KTD) Phase III (Package A)-Chilled Water Pipe Laying Works

No information was provided from the Contractor.

 

MTR projects

Contract No.

Project Title

Site Activities

1107

Diamond Hill to Kai Tak Tunnels

1)    Site investigation works

2)    Investigation and removal of old foundation works

3)    Sheet piling works

4)    Shaft excavation

5)    Site preparation works

6)    Grouting works

1108

Kai Tak Station and Associated Tunnels

1)    Excavation and shotcreting on excavated slope

2)    Breaking of existing underground boulder

3)    Disposal of marine deposit

4)    Station structure: track slab concreting, rebar fixing, formwork erection

5)    SCL1107/1108 interface stub tunnel ELS

6)    Mined tunnel: jet grouting; sheet piling for water cut off wall by silent pile

7)    Base lab construction

1108A

Kai Tak Barging Point Facilities

1)    Spoil Disposal

2)    Watering of Site

3)    Vehicular Gate Installation

1109

Shatin to Central Link: Ma Tau Wai and To Kwa Wan Stations and Tunnels

1)    TAM Grouting

2)    Archaeological Survey

3)    Socketted H Piling

4)    Proof-drilling

5)    Bulk Excavation

6)    Traffic Diversion

7)    Strut Installation

8)    Sheet Piling

9)    TBM Set up works

 

HKHA projects

Contract No.

Project Title

Site Activities

20130225

Foundation for Public Rental Housing Development at Ex-Kwai Chung Police Married Quarters (Kai Tak 1G1(B) Site)

No information was provided from the Contractor.

 

URA projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6515

Kai Tak Flat-For-Flat Development

1)    Environmental monitoring works

2)    H1 construction of typical floor 10/F~14/F

3)    H2 construction of typical floor 10/F~14/F

4)    H3 construction of typical floor 10/F~14/F

5)    L1 construction of typical floor 4/F~R/F

6)    Retail block – concreting to footing

7)    E&M installation

8)    Brown area – installation of ELS works for manhole

 

COHL projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6516 & 6517

New Kowloon Inland Lot No. 6516 & 6517 - Proposed Residential Development

No information was provided from the Contractor.

 


List of Temporary Government Land Allocations (TGLAs)

TGLA No.

Name of Occupants

Site Activities

GLA-TNK 1591

CE/LW, Civil Engineering & Development Department

Works area

GLA-TNK 1751

Housing Department

Works Area and Storage Area

GLA-TNK 1801

Housing Department

Works and storage area (Site 1B3)

GLA-TNK 1177

Electrical and Mechanical Services Department

Vehicle maintenance depot next to the existing HATCL II Building

GLA-TNK 1338

Highways Department

Maintenance Depot; off Cargo Circuit

GLA-TNK 1635

CE/SP, Drainage Services Department

Works Area

GLA-TNK 1713

CHE/K, Highways Department

Storage

GLA-TNK 1749

CE/SP, Drainage Services Department

Additional Works area

GLA-TNK 1568

Fire Services Department

Driving training ground

GLA-TNK 1360

HK Police Force

Storage of police water barriers and metal gates

GLA-TNK 1675

PM(K), Civil Engineering & Development Department

Works Area

GLA-TNK 1760

CE/DP, Drainage Services Department

Site office and storage area

GLA-TNK 1646

CGE/LPM, Civil Engineering and Development Department

Stockpiling of excavated & construction materials

GLA-TNK 1608

Transport Department

Works Area

GLA-TNK 1580

PM(K), Civil Engineering & Development Department

Works Area

GLA-TNK 1581

PM(K), Civil Engineering & Development Department

Works Area

 

 

GLA-TNK 1334

CE/Construction, Water Supplies Department

Works Area

GLA-TNK 1144

CE/PW, Civil Engineering and Development Department

Works Area

GLA-TNK 1226

GLA-TNK 1191

Hong Kong Observatory

Automatic Weather station

GLA-TNK 1542

Weather Station

GLA-TNK 1507

CE/SD, Civil Engineering and Development Department

Barging point and storage area

GLA-TNK 1671

Civil Engineering and Development Department

Works Area/Engineer’s & Contractor’s Accommodation/Fabrication Yard

GLA-TNK 1707

PM(K), Civil Engineering & Development Department

Works Area/Stockpiling Area

 

 

 

GLA-TNK 1759

PM(K), Civil Engineering & Development Department

Works Area

GLA-TNK 1823

PM(K), Civil Engineering & Development Department

Works Area

GLA-TNK 1850

PM(K), Civil Engineering & Development Department

Works Area

GLA-TNK 1548

CE/PM, Water Supplies Department

Works Area

GLA-TNK 1571

ArchSD

Works Area

GLA-TNK 1692

CE/CM, Drainage Supplies Department

Works Area

GLA-TNK 1693

Architectural Services Department

Works Area/Stockpiling area

GLA-TNK 1899

CE/K, Water Supplies Department

Works Area

GLA-TNK 1717

EMSD

Works Area/Stockpiling Area/Site Office for DCS

GLA-TNK 1814

CMP 202, Architectural Services Department

Works Area

GLA-TNK 1821

CE/Municipal, EMSD

Works/Storage Area

GLA-TNK 1862

CE/PM, DSD

Works Area

GLA-TNK 1885

ArchSD

Barging Point

 


List of Short Term Tenancy (STT)

STT No.

Name of Occupants

Site Activities

KX2688

Goldway Parking Ltd.

Car-park

KX2345

CLP Power Hong Kong Limited

Storage of construction materials and plant equipment

KX2662

Hong Kong Cricket Association

Operation of Hong Kong Cricket Association

KX2628

Moral Well International Enterprise Limited

Car-park

KX2552

Era International Investment Limited

Car-park

KX2629

Graceful Ocean Development Limited

Car-park

KX2261

Hong Kong Aviation Club Ltd.

Training for air traffic controllers

KX2574

Future Chinese Limited

Car-park

KX2575

Nanjing Limited

Car-park

KX2109

Multi-Light Limited

1) Concrete production

2) Storage of building materials

KX2675

Wang Lee Building Materials Trading Ltd.

Operation of business in the recovery and recycling

KX2676

Ga Shing Transport Co.

Operation of business in the recovery and recycling

KX2677

Chuen Kee Metal Trading Co Ltd.

Operation of business in the recovery and recycling

KX2678

Kin Xun Environment Recycle Ltd

Operation of business in the recovery and recycling

KX2569

Sureguard Logistics Limited

Open storage of goods and dangerous goods

KX2641

Citybus Limited

Parking of buses

KX2642

Goldway Parking Ltd.

Car-park

KX2189

The Hong Kong Housing Authority

Site and road formation, building and associated works for the development of the premises

KX2190

KX2616

CLP Power Hong Kong Limited

Constructing, maintaining and operating Underground  Strata I and II and The Pink Edged Red Area

 


1.10          The construction programme showing the inter-relationship with environmental protection/mitigation measures are presented in Table 1.3. 

 

Table 1.3 Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures

Construction Works

Major Environmental Impact

Control Measures

As mentioned in Table 1.2

Noise, dust impact, water quality and waste generation

Ÿ   Sufficient watering of the works site with active dust emitting activities

Ÿ   Properly cover the stockpiles

Ÿ   On-site waste sorting and implementation of trip ticket system

Ÿ   Appropriate desilting/sedimentation devices provided on site for treatment before discharge

Ÿ   Use of quiet plant and well-maintained construction plant

Ÿ   Provide movable noise barrier

Ÿ   Provide sufficient mitigation measures as recommended in Approved EIA Report/Lease requirement

Ÿ   Provide silt curtain for dredging and filling activities

Summary of EM&A Requirements

 

1.11          The EM&A programme requires construction noise monitoring, air quality monitoring, landscape and visual monitoring and environmental site audit.  The EM&A requirements for each parameter are described in the following sections, including:

 

·          All monitoring parameters;

·          Action and Limit levels for all environmental parameters;

·          Event Action Plans;

·          Environmental mitigation measures, as recommended in the Schedule 3 EIA Report; and

·          Environmental requirements in contract documents under Contract No. KLN/2013/16.

 

1.12          The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 6 of this report.

 

1.13          This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the required monitoring parameters, namely air quality and noise levels and audit works for the Project in June 2014.