1.1
The Kai Tak Development (KTD) is located in
the south-eastern part of Kowloon Peninsula, comprising the apron and runway
areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon
Bay, Kwun Tong and Cha Kwo
Ling. It covers a land area of about 328 hectares. The Project also covers
Kowloon Bay and Kwun Tong Typhoon Shelter and the
adjacent water bodies. The general layout of the Project is shown in Figure
1.
1.2
Civil Engineering and Development Department (CEDD) had completed an Environmental Impact Assessment (EIA) study for KTD under Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study cum Design and
Construction of Advance Works ¡V
Investigation, Design and Construction (hereafter called ¡§Schedule 3 EIA Report¡¨).
The Schedule 3 EIA Report was approved under Environmental Impact Assessment
Ordinance (EIAO) in March 2009.
1.3
As recommended in the Schedule 3 EIA Report, EM&A programme shall be
required for different phases of the KTD as a whole. In March 2017, Castco Testing Centre Limited (CTCL) was commissioned by CEDD to undertake the Environmental Monitoring and
Audit (EM&A) works for KTD. Under the Contract, Environmental Team (ET)
shall oversee all the environmental issues within the Kai Tak
Development (KTD).
1.4
CTCL was commissioned by CEDD to undertake the Environmental Monitoring
and Audit (EM&A) works for KTD Contract No. KLN/2016/09
starting from 3 March 2017. This is the 26th
Monthly
EM&A report summarizing the EM&A works for the Project in April 2019.
1.5
Different parties with different levels of involvement in the project
organization include:
¡P
Environmental Protection Department (The Authority)
¡P
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
¡P
The Engineer and the Engineer¡¦s Representative (ER) ¡V Acuity Sustainability Consulting Limited (Acuity)
¡P
Environmental Team (ET) ¡V Castco Testing Centre Limited (CTCL)
¡P
Independent Environmental Checker (IEC) ¡V Ka Shing management
consultant Limited (Ka Shing)
1.6
The key contacts of the Project are shown in Table 1.1.
Table 1. 1 Key Project
Contacts
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
CEDD |
Project
Proponent |
Mr. WT Chau |
3106
2584 |
3579
4512 |
Mr. Kenny Chan |
3104
2142 |
|||
Acuity |
Engineer¡¦s
Representative (ER) |
Mr. Kevin Li |
2698
6833 |
2333
1316 |
Castco |
Environmental
Team (ET) |
Ms. Mio Leong |
2597
8387 |
2597
8399 |
Ka Shing |
Independent
Environmental Checker (IEC) |
Dr. C.F. Ng |
2618
2166 |
2120
7752 |
Construction Activities undertaken during the
Reporting Month
1.7
There are several works contracts undertaken within KTD during the
reporting month. In order to collect relevant environmental information from
the work contracts and incorporate into this monthly monitoring report, a
survey form for monthly environmental performance records was sent to all work
contracts/tenants within KTD on 31 March 2019. The survey form shall be returned by 5th of each month to provide the environmental
monthly information of respective work contracts within KTD.
1.8
Based on the returned survey form from work contracts and site
observation for short term tenancy (STT) / temporary government land allocation
(TGLA) during the weekly site inspection, the major site activities undertaken
within Kai Tak Development (KTD) in the reporting
month are summarized in Table 1.2.
KDO, CEDD projects |
||
Contract
No. |
Project
Title |
Site
Activities |
KL/2011/01 |
Kai Tak Development-Reconstruction
and Upgrading of Kai Tak Nullah |
1)
Construction of box culvert |
|
Kai Tak Development ¡V Stage 3A infrastructure at Former North Apron
Area |
1)
Site Clearance |
KL/2012/03 |
Kai Tak Development ¡V Stage 4 Infrastructure
at Former North Apron Area |
1)
Finishing
works, E&M work in PS2,NPS 2)
Site
clearance works, installation of insulation layer in DCS 3)
Road
widening works (Construction of U-channels) in (Portion 1) Sung Wong Toi Road 4)
Installation
of drainage pipe, pressure test for water main, UU laying works and Road
works in Road D2. 5)
Removal
of excavated material in Portion 6. |
KL/2014/01 |
Kai Tak
Development ¡V Stage 2 Infrastructure Works for Developments at
The Southern Part of the Former Runway |
1) Laying of sewer, drainage and pavement 2) TTA implementation, junction improvement works at
Shing Fung Road, Wang Chiu Road / Sheung Yee Road and Wang Chiu Road / Kai Cheung Road; 3) ELS installation and construction of box culvert
and underpass; 4) Construction of utilities trough at Kai Tak Bridge; 5) Construction of pile caps, noise barrier
footings, outfalls, deck structure and columns. |
KL/2014/03 |
Kai Tak
Development ¡V Stage 3 Infrastructure Works for Developments at the Southern Part
of the Former Runway |
1) Construction of Tunnel Box Structure; 2) Construction of Drainage and Sewerage Works 3) Construction of Subway 4) Construction of DCS 5) Backfilling |
KL/2015/02 |
Kai Tak
Development ¡V
Stage 5A infrastructure at Former North Apron
Area |
1) Excavate with ELS
works for subway construction at PERE 2) Structural works for subway SW6 from CH0 to Ch20
and Staircase ST3 3) Structural works for pile caps at the existing
Bridge K72 4) Carry out trial pits for subway construction at
layby of PERE (Stage 4) 5) Remedial works and application of joint sealant
in box culverts 6) Construction of box culvert B5 connection 7) Preparation works for temporary flow diversion at
upstream connection 8) DCS works at Portion 6, Road D1 9) DCS works at Portion 1, Road L7 10) Drainage works at Portion 1, Road L7 11) Watermains laying works at Portion 1, Road L7 12) Drainage and Sewerage works in Portion 2&3 |
KL/2015/03 |
Kai Tak
Development ¡V Stage 3B Infrastructure at former North Apron Area |
1) Site Clearance for all possessed portion 2) Erection of Site Boundary Fencing /Hoarding 3) Tree Transplanting & Tree Felling 4) Piling Works for P5, P6 & P7 of Walkway LW4 5) Construction of temporary support along PERE for
demolition of composite structure of existing Flyover K9 6) ELS and Excavation for SW4 7) Backfilling works at original location of Tree
T285 8) Reinstatement of King Tai Street |
WSD
projects |
||
Contract
No. |
Project
Title |
Site
Activities |
6/WSD/08 |
Replacement and
Rehabilitation of Water Mains Stage 2&3 |
1)
Construction material storage (Portion 2-3) |
7/WSD/08 |
1) Storage
of water works material |
ArchSD
projects |
||
Contract
No. |
Project
Title |
Site
Activities |
SS E517 |
Construction site of 30-classroom secondary
school at Site 1A-2, Kai Tak |
1)
Construction of last storm water manhole at
north-east site corner |
SS C503 |
Design and Construction of Kowloon East Regional
Headquarters and Operational Base cum Ngau Tau Kok Divisional Police Station at 105 Concorde Road, Kai Tak |
1)
Rebar fixing, formwork erection and concreting of
pile caps and columns / walls; 2)
Backfilling soil from pile cap levels to G/F
levels; 3)
PDA tests and loading tests of driven H-piles; 4)
Driving and welding works of sheet piles; 5)
Proof drill works; 6)
Welding works of H-pile pile heads; 7)
Demolition of Visual Mock Up of Curtain Wall; 8)
Waterproofing works of basement structure |
EMSD projects |
||
Contract
No. |
Project
Title |
Site
Activities |
1020EM12A |
District Cooling System (DCS) at Kai Tak Development
(KTD) Phase III (Package A) - Chilled Water Pipe Laying
Works |
1)
Excavation 2)
Pipe Laying |
2477EM14A |
District Cooling System (DCS) at Kai Tak Development (KTD) Phase
III (Package B) - Water Pipe Laying Works |
1)
Levelling of Ground Surface |
2487EM14W |
District Cooling System (DCS) at Kai Tak Development (KTD) Phase
III (Package B) -Electrical and Mechanical Installation |
1)
E&M installation inside North DCS
Plant 2)
E&M installation inside South DCS
Plant 3)
E&M installation inside Site 1A2 4)
E&M installation inside Site 1E2 |
HyD projects |
||
Contract No. |
Project Title |
Site Activities |
HY/2014/18 |
Provision
of Barrier-Free Access Facilities for Highway Structures - Phase 3 Contract 7 |
1) Formwork construction |
HY/2014/07 |
Central
Kowloon Route - Kai Tak West |
1)
Piling
Works |
MTR projects |
||
Contract No. |
Project Title |
Site Activities |
SCL1108 |
Kai Tak Station and Associated Tunnels |
1) Open cut tunnel: General cleaning and defect
rectification and SUA EVA construction; 2) Cut and cover tunnel: General cleaning and defect
rectification; 3) Station: F.F.L. in Area 3, installation of roof
cladding and reflected ceiling at Entrance A, B & D, installation of
glass canopy at DEE and SEE, installation of aluminum
fins and external cladding at NVS and SVS, and installation of metal screen
wall at DEE and SEE. |
SCL1109 |
Shatin to
Central Link: Ma Tau Wai and To Kwa Wan Stations and
Tunnels |
1)
Backfilling 2)
Construction of RC structure 3)
Traffic diversion 4)
UU diversion |
SCL1123 |
Exhibition
Station and Western Approach
Tunnel |
1) General site clearance 2) Spoil Disposal |
HKHA
projects |
||
Contract
No. |
Project
Title |
Site
Activities |
20150362 |
Construction of Home Ownership Scheme
at Kai Tak Site 1G1(B) |
1) Metal
formwork erection 2) Metal
formwork dismantling 3) Concreting 4) Precast
elements installation 5) Rebar
fixing 6) Painting 7) Drainage
pipes lying |
Poly
Property projects |
||
Contract No. |
Project Title |
Site Activities |
New
Kowloon Inland Lot No. 6562
& 6565 |
New Kowloon Inland Lot No. 6562 -
Residential Development at
Kai Tak Area 1K Site 3 |
1)
Piling
Works |
New
Kowloon Inland Lot No. 6565 |
New Kowloon Inland Lot No. 6565 -
Residential Development at
Kai Tak Area 1L Site 3 |
1)
Piling
Works |
HKICIM
Group projects |
||
Contract
No. |
Project
Title |
Site
Activities |
New
Kowloon Inland Lot No. 6563 -
Residential Development at Kai Tak Area 1L Site 1 |
1)
Piling
Works |
|
New
Kowloon Inland Lot No.
6564 |
New Kowloon Inland Lot No. 6564 - Residential Development ta Kai Tak Area 1L
Site 2 |
1)
Piling
Works |
Contract No. |
Project Title |
Site Activities |
New Kowloon Inland Lot No. 6557 |
New
Kowloon Inland Lot No. 6557 - Commercial
Development |
1)
Diaphragm
Wall Works (Site B) 2)
Predrilling
Works (Site A & B) 3)
Pipe
Pile Works (Site A & B) 4)
Bored
Pile Works (Site A) |
Century
Basis Limited projects |
||
Project Title |
Site Activities |
|
New Kowloon Inland Lot No. 6566 |
New
Kowloon Inland Lot No. 6566 - Residential
Development |
1)
Loading
Test 2)
ELS |
Century
Base Development Limited projects |
||
Contract No. |
Project Title |
Site Activities |
New
Kowloon Inland Lot No.6567 |
New Kowloon Inland Lot No. 6567 - Residential Development |
1)
Pile
Cap |
1.9
The construction programme showing the inter-relationship with
environmental protection/ mitigation measures are presented in Table 1.3.
Table 1. 3 Construction
Programme Showing the Inter-Relationship with Environmental
Protection/Mitigation Measures
|
Major Environmental Impact |
Control Measures |
As mentioned in Table
1.2 |
Noise, dust impact,
water quality and waste generation |
¡P
Sufficient watering of
the
works site with
active
dust emitting
activities ¡P
Properly cover the
stockpiles ¡P
On-site waste sorting
and
implementation
of
trip ticket system ¡P
Appropriate
distilling/ sedimentation devices provided onsite for treatment before discharge ¡P
Use of quiet plant and
well-maintained construction plant ¡P
Provide movable
noise
barrier ¡P
Provide sufficient
mitigation
measures as
recommended in
Approved
EIA Report/ Leas requirement |
1.10
The EM&A programme requires construction noise monitoring, air quality
monitoring, landscape and visual monitoring and environmental site audit. The
EM&A requirements for each parameter are described in the following
sections, including:
¡P
All monitoring parameters;
¡P
Action and Limit levels for all environmental parameters;
¡P
Event Action Plans;
¡P
Environmental mitigation measures, as recommended in the Schedule 3 EIA
Report; and Environmental requirements in contract documents under Contract No.
KLN/2016/09.
1.11
The advice on the implementation status of environmental protection and
pollution control/mitigation measures is summarized in Section 6 of this
report.
1.12
This report presents the monitoring results, observations, locations,
equipment, period, methodology and QA/QC procedures of the required monitoring
parameters, namely air quality and noise levels and audit work for the Project
in April 2019.