1.                  INTRODUCTION

 

Background


 

1.1              The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It covers a land area of about 328 hectares. The Project also covers Kowloon Bay and Kwun Tong Typhoon Shelter and the adjacent water bodies. The general layout of the Project is shown in Figure 1.

 

1.2              Civil Engineering and Development Department (CEDD) had completed an Environmental Impact Assessment (EIA) study for KTD under Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works ¡V Investigation, Design and Construction (hereafter called ¡§Schedule 3 EIA Report¡¨). The Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance (EIAO) in March 2009.

 

1.3              As recommended in the Schedule 3 EIA Report, EM&A programme shall be required for different phases of the KTD as a whole. In March 2017, Castco Testing Centre Limited (CTCL) was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD. Under the Contract, Environmental Team (ET) shall oversee all the environmental issues within the Kai Tak Development (KTD).

 

1.4              CTCL was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD Contract No. KLN/2016/09 starting from 3 March 2017. This is the 26th Monthly EM&A report summarizing the EM&A works for the Project in April 2019.

 

Project Organizations

 

1.5              Different parties with different levels of involvement in the project organization include:

¡P                     Environmental Protection Department (The Authority)

¡P                     Project Proponent ¡V Civil Engineering and Development Department (CEDD)

¡P                     The Engineer and the Engineer¡¦s Representative (ER) ¡V Acuity Sustainability Consulting Limited (Acuity)

¡P                     Environmental Team (ET) ¡V Castco Testing Centre Limited (CTCL)

¡P                     Independent Environmental Checker (IEC) ¡V Ka Shing management consultant Limited (Ka Shing)


 

 


1.6              The key contacts of the Project are shown in Table 1.1.

 

Table 1. 1       Key Project Contacts

Party

Role

Contact Person

Phone No.

Fax No.

CEDD

Project Proponent

Mr. WT Chau

3106 2584

3579 4512

Mr. Kenny Chan

3104 2142

Acuity

Engineer¡¦s Representative (ER)

Mr. Kevin Li

2698 6833

2333 1316

Castco

Environmental Team (ET)

Ms. Mio Leong

2597 8387

2597 8399

Ka Shing

Independent Environmental Checker (IEC)

Dr. C.F. Ng

2618 2166

2120 7752

Construction Activities undertaken during the Reporting Month

 

1.7              There are several works contracts undertaken within KTD during the reporting month. In order to collect relevant environmental information from the work contracts and incorporate into this monthly monitoring report, a survey form for monthly environmental performance records was sent to all work contracts/tenants within KTD on 31 March 2019. The survey form shall be returned by 5th of each month to provide the environmental monthly information of respective work contracts within KTD.

 

1.8              Based on the returned survey form from work contracts and site observation for short term tenancy (STT) / temporary government land allocation (TGLA) during the weekly site inspection, the major site activities undertaken within Kai Tak Development (KTD) in the reporting month are summarized in Table 1.2.

 


Table 1. 2       Summary Table for Major Site Activities undertaken within KTD in the Reporting Month


KDO, CEDD projects

Contract No.

Project Title

Site Activities

KL/2011/01

Kai Tak Development-Reconstruction and Upgrading of Kai Tak Nullah

1)      Construction of box culvert

KL/2012/02

Kai Tak Development ¡V Stage 3A infrastructure at Former North Apron Area

1)      Site Clearance

KL/2012/03

Kai Tak Development ¡V Stage 4 Infrastructure at Former North Apron Area

1)          Finishing works, E&M work in PS2,NPS

2)          Site clearance works, installation of insulation layer in DCS

3)          Road widening works (Construction of U-channels) in (Portion 1) Sung Wong Toi Road

4)          Installation of drainage pipe, pressure test for water main, UU laying works and Road works in Road D2.

5)          Removal of excavated material in Portion 6.

KL/2014/01

Kai Tak Development ¡V Stage 2 Infrastructure Works for Developments at The Southern Part of the Former Runway

1)      Laying of sewer, drainage and pavement

2)      TTA implementation, junction improvement works at Shing Fung Road, Wang Chiu Road / Sheung Yee Road and Wang Chiu Road / Kai Cheung Road;

3)      ELS installation and construction of box culvert and underpass;

4)      Construction of utilities trough at Kai Tak Bridge;

5)      Construction of pile caps, noise barrier footings, outfalls, deck structure and columns.

KL/2014/03

Kai Tak Development ¡V Stage 3 Infrastructure Works for Developments at the Southern Part of the Former Runway

1)      Construction of Tunnel Box Structure;

2)      Construction of Drainage and Sewerage Works

3)      Construction of Subway

4)      Construction of DCS

5)      Backfilling

KL/2015/02

Kai Tak Development ¡V Stage 5A infrastructure at Former North Apron Area

1)     Excavate with ELS works for subway construction at PERE

2)     Structural works for subway SW6 from CH0 to Ch20 and Staircase ST3

3)     Structural works for pile caps at the existing Bridge K72

4)     Carry out trial pits for subway construction at layby of PERE (Stage 4)

5)     Remedial works and application of joint sealant in box culverts

6)     Construction of box culvert B5 connection

7)     Preparation works for temporary flow diversion at upstream connection

8)     DCS works at Portion 6, Road D1

9)     DCS works at Portion 1, Road L7

10) Drainage works at Portion 1, Road L7

11) Watermains laying works at Portion 1, Road L7

12) Drainage and Sewerage works in Portion 2&3

KL/2015/03

Kai Tak Development ¡V Stage 3B Infrastructure at former North Apron Area

1)  Site Clearance for all possessed portion

2)  Erection of Site Boundary Fencing /Hoarding

3)  Tree Transplanting & Tree Felling

4)  Piling Works for P5, P6 & P7 of Walkway LW4

5)  Construction of temporary support along PERE for demolition of composite structure of existing Flyover K9

6)  ELS and Excavation for SW4

7)  Backfilling works at original location of Tree T285

8)  Reinstatement of King Tai Street

 

WSD projects

Contract No.

Project Title

Site Activities

6/WSD/08

Replacement and Rehabilitation of Water Mains Stage 2&3

1)      Construction material storage (Portion 2-3)

7/WSD/08

1)      Storage of water works material

 

ArchSD projects

Contract No.

Project Title

Site Activities

SS E517

Construction site of 30-classroom secondary school at Site 1A-2, Kai Tak

1)          Construction of last storm water manhole at north-east site corner

SS C503

Design and Construction of Kowloon East Regional Headquarters and Operational Base cum Ngau Tau Kok Divisional Police Station at 105 Concorde Road, Kai Tak

1)          Rebar fixing, formwork erection and concreting of pile caps and columns / walls;

2)          Backfilling soil from pile cap levels to G/F levels;

3)          PDA tests and loading tests of driven H-piles;

4)          Driving and welding works of sheet piles;

5)          Proof drill works;

6)          Welding works of H-pile pile heads;

7)          Demolition of Visual Mock Up of Curtain Wall;

8)          Waterproofing works of basement structure

 

EMSD projects

Contract No.

Project Title

Site Activities

1020EM12A

District Cooling System (DCS) at Kai Tak Development (KTD) Phase III (Package A) - Chilled Water Pipe Laying Works

1)     Excavation

2)     Pipe Laying

2477EM14A

District Cooling System (DCS) at Kai Tak Development (KTD) Phase III (Package B) - Water Pipe Laying Works

1)     Levelling of Ground Surface

 

2487EM14W

District Cooling System (DCS) at Kai Tak Development (KTD) Phase III (Package B) -Electrical and Mechanical Installation

1)       E&M installation inside North DCS Plant

2)       E&M installation inside South DCS Plant

3)       E&M installation inside Site 1A2

4)       E&M installation inside Site 1E2

 

HyD projects

Contract No.

Project Title

Site Activities

HY/2014/18

Provision of Barrier-Free Access Facilities for Highway Structures - Phase 3 Contract 7

1)      Formwork construction

HY/2014/07

Central Kowloon Route - Kai Tak West

1)      Piling Works

 

MTR projects

Contract No.

Project Title

Site Activities

SCL1108

Kai Tak Station and Associated

Tunnels

1)      Open cut tunnel: General cleaning and defect rectification and SUA EVA construction;

2)      Cut and cover tunnel: General cleaning and defect rectification;

3)      Station: F.F.L. in Area 3, installation of roof cladding and reflected ceiling at Entrance A, B & D, installation of glass canopy at DEE and SEE, installation of aluminum fins and external cladding at NVS and SVS, and installation of metal screen wall at DEE and SEE.

SCL1109

Shatin to Central Link: Ma Tau

Wai and To Kwa Wan Stations

and Tunnels

1)      Backfilling

2)      Construction of RC structure

3)      Traffic diversion

4)      UU diversion

SCL1123

Exhibition Station and Western

Approach Tunnel

1)      General site clearance

2)      Spoil Disposal

 

HKHA projects

Contract No.

Project Title

Site Activities

20150362

Construction of Home Ownership Scheme at Kai Tak Site 1G1(B)

1)      Metal formwork erection

2)      Metal formwork dismantling

3)      Concreting

4)      Precast elements installation

5)      Rebar fixing

6)      Painting

7)      Drainage pipes lying

 

Poly Property projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6562 & 6565

New Kowloon Inland Lot No. 6562 - Residential Development at Kai Tak Area 1K Site 3

1)      Piling Works

New Kowloon Inland Lot No. 6565

New Kowloon Inland Lot No. 6565 - Residential Development at Kai Tak Area 1L Site 3

1)          Piling Works

 

HKICIM Group  projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6563

New Kowloon Inland Lot No. 6563 - Residential Development at Kai Tak Area 1L Site 1

1)          Piling Works

New Kowloon Inland Lot No. 6564

New Kowloon Inland Lot No. 6564 - Residential Development ta Kai Tak Area 1L Site 2

1)          Piling Works

 

 

 

 

Leader Bright Limited projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6557

New Kowloon Inland Lot No. 6557 - Commercial Development

1)          Diaphragm Wall Works (Site B)

2)          Predrilling Works (Site A & B)

3)          Pipe Pile Works (Site A & B)

4)          Bored Pile Works (Site A)

 

Century Basis Limited projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No. 6566

New Kowloon Inland Lot No. 6566 - Residential Development

1)          Loading Test

2)          ELS

 

Century Base Development Limited projects

Contract No.

Project Title

Site Activities

New Kowloon Inland Lot No.6567

New Kowloon Inland Lot No. 6567 - Residential Development

1)          Pile Cap

 

 


1.9              The construction programme showing the inter-relationship with environmental protection/ mitigation measures are presented in Table 1.3.

 

Table 1. 3       Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures

 

Construction Works

Major Environmental Impact

Control Measures

As mentioned in Table 1.2

Noise, dust impact, water quality and waste generation

¡P         Sufficient watering of the works site with active dust emitting activities

¡P         Properly cover the stockpiles

¡P         On-site waste sorting and implementation of trip ticket system

¡P         Appropriate distilling/ sedimentation devices provided onsite for treatment

before discharge

¡P         Use of quiet plant and well-maintained construction plant

¡P         Provide movable noise barrier

¡P         Provide sufficient mitigation measures as recommended in Approved EIA Report/ Leas requirement

 

 

 

Summary of EM&A Requirements

 

1.10          The EM&A programme requires construction noise monitoring, air quality monitoring, landscape and visual monitoring and environmental site audit. The EM&A requirements for each parameter are described in the following sections, including:

 

¡P         All monitoring parameters;

¡P         Action and Limit levels for all environmental parameters;

¡P         Event Action Plans;

¡P         Environmental mitigation measures, as recommended in the Schedule 3 EIA Report; and Environmental requirements in contract documents under Contract No. KLN/2016/09.

 

1.11          The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 6 of this report.

 

1.12          This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the required monitoring parameters, namely air quality and noise levels and audit work for the Project in April 2019.