1.                  INTRODUCTION

Background

 

1.1              The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula, comprising the apron and runway areas of the former Kai Tak Airport and existing waterfront areas at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It covers a land area of about 328 hectares. The Project also covers Kowloon Bay and Kwun Tong Typhoon Shelter and the adjacent water bodies. The general layout of the Project is shown in Figure 1.

 

1.2              Civil Engineering and Development Department (CEDD) had completed an Environmental Impact Assessment (EIA) study for KTD under Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works ¡V Investigation, Design and Construction (hereafter called ¡§Schedule 3 EIA Report¡¨). The Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance (EIAO) in March 2009.

 

1.3              As recommended in the Schedule 3 EIA Report, EM&A programme shall be required for different phases of the KTD as a whole. In August 2010, Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD.  Under the Contract, Environmental Team (ET(KTD)) shall oversee all the environmental issues within the Kai Tak Development (KTD), including but not limit to the Schedule 2 Designated Projects and other work contracts.

 

1.4              Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental Monitoring and Audit (EM&A) works for KTD.  This is the 4th Monthly EM&A report summarizing the EM&A works for the Project in April 2011.

Project Organizations

 

1.5              Different parties with different levels of involvement in the project organization include:

¡P          Environmental Protection Department (The Authority);

¡P          Project Proponent ¡V Civil Engineering and Development Department (CEDD).

¡P          The Engineer and the Engineer¡¦s Representative (ER) ¡V AECOM.

¡P          Environmental Team (ET(KTD)) ¡V Cinotech Consultants Limited (CCL).

¡P          Independent Environmental Checker (IEC(KTD)) ¡V Allied Environmental Consultants Limited (AEC).


1.6              The key contacts of the Project are shown in Table 1.1.

Table 1.1    Key Project Contacts

Party

Role

Contact Person

Phone No.

Fax No.

CEDD

Project Proponent

Mr. K Y SHIN

2301 1461

2301 1277

Mr. William WONG

3104 2197

2301 1277

AECOM

Engineer¡¦s  Representative

Ms. Anna CHUNG

3105 8516

2891 0305

Cinotech

Environmental Team (KTD)

Dr. Priscilla Choy

2151 2089

3107 1388

Ms. Ivy Tam

2151 2090

AEC

Independent Environmental Checker (KTD)

Ms. Grace Kwok

2815 7028

2815 5399

Construction Activities undertaken during the Reporting Month

 

1.7              There are several works contracts undertaken within KTD during the reporting month.  In order to collect relevant environmental information from the work contracts and incorporate into this monthly monitoring report, a survey form for monthly environmental performance records was sent to all work contracts/tenants within KTD on 30 November 2010. The survey form shall be returned by 5th each month to provide the environmental monthly information of respective work contracts within KTD.

 

1.8              Based on the returned survey form from work contracts and site observation for short term tenancy (STT) / temporary government land allocation (TGLA)  during the weekly site inspection, the major site activities undertaken within Kai Tak Development (KTD) in the reporting month are summarized in Table 1.2:

Table 1.2    Summary Table for Major Site Activities undertaken within KTD in the Reporting month

 

KDO, CEDD projects

Contract No.

Project Title

Site Activities

KL/2009/01

Site Formation for Kai Tak Cruise Terminal

1)    Piling Works

2)    Installation of precast frontal panels

3)    Dredging Works

4)    Installation of temporary steel bracing

5)    Sorting of C&D material from existing seawall

6)    Erection and maintenance of silt curtain

7)    Impact water quality monitoring/surveillance system

KL/2008/09

Stage 1 Infrastructure works at North Apron

1)    Drainage Works

2)    Watermain Works

3)    Footbridge Superstructure construction

4)    Construction of subway extension

5)    Road Works

KL/2008/07

Stage 1 Advance Infrastructure Works

1)    Construction of sewage pumping station

2)    Laying of drainage, sewerage and waterworks at Road TD3

3)    Waterworks at Road TL14

4)    Watermain laying at Hoi Bun Road

5)    Junction improvement works at Wang Chiu Road

6)    Filling for public landing steps cum fireboat berth

7)    Pipe jacking of watermain across Wang Chiu Road

8)    Construction of superstructure of the sewage pumping station

KL/2009/02

Site Investigation for Trunk Road T2 and Infrastructure at South Apron (Stage 1)

1)    Instrument monitoring

 

 

CEO, CEDD project

Contract No.

Project Title

Site Activities

CV/2007/03

Development at Anderson Road

Disposal of inert C&D material at Kai Tak

 

DSD project

Contract No.

Project Title

Site Activities

DC/2008/12

Sewage Interception Scheme in Kowloon City

1)    Construction of substructure of pumping stations

2)    Laying of twin rising mains by open trench method

3)    Construction of chambers, manholes etc.

4)    Backfilling of trenches for rising mains

5)    Laying of gravity sewers in To Kwa Wan Road

6)    Waterproofing & backfilling works for pumping stations

7)    Construction of superstructure of pumping stations

DC/2010/03

 

Kai Tak Nullah Improvement Works at Prince Edward Road East

1)    Maintain Engineer¡¦s Principal Office

2)    Maintain Contractor¡¦s Site Office and Site Compound

3)    Construction of Box Culvert bay 1A-a

DC/2009/21

Provision of Interception Facilities at Jordan Valley Box Culvert

1)    Sheet Piling for Impermeable Wall

2)    Bored Piling

3)    Excavation

4)    Tree Transplantation

 

HD projects

Contract No.

Project Title

Site Activities

20090097

Public Rental Housing Development at Kai Tak Site 1A

1)    Construction of Superstructure (6 blocks)

2)    External Works

20090006

Public Rental Housing Development at Kai Tak Site 1B

1)    Construction of Substructure works

2)    Construction of Superstructure works

3)    Construct of VPB Study Mock-up

4)    Construction of Precast Water Tank

 

WSD project

Contract No.

Project Title

Site Activities

16/WSD/06

Replacement and Rehabilitation of Water Mains Stages 2 & 3

Handover the Area back to LandsD on 1 April 2011

26/WSD/06

3/WSD/08

1)    Site Office of the Contractor

2)    Storage of water works material

3)    Storage and sorting of C&D materials

6/WSD/08

1)    Construction material storage (Portion DX1)

2)    C&D material storage (Portion D1)

7/WSD/08

1)    Transportation and storage of pipe works material (Portion BX1)

2)    Transportation and sorting of construction waste (Portion BX1)

3)    Fabrication of special pipe fittings (Portion B1)

8/WSD/08

1)    C&D materials storage (Portion E1)

2)    Pipe materials storage (Portion E2)

 

ArchSD project

Contract No.

Project Title

Site Activities

SS W 303

Kai Tak Cruise Terminal Building and Ancillary Facilities

1)     Construction pile caps

2)     Driven H-pile works

3)     Mobilization and set up concrete pre-cast yard at Area B & C

4)     Tree nursery

5)     ELS, excavation and pile caps

6)     Tower crane foundation construction

TCT323

Ground Investigation works for ¡§Establishment for Centre of Excellence in Paediatrics¡¨

1)    Ground Investigation Works

 

CLP projects

Contract No.

Project Title

Site Activities

 

Kai Tak Cruise Terminal Cable Tunnel

No civil activity

Eastern Road Substation

No civil activity

CKL-KCT circuit 1&2

CLPP (132kV cable installation)

132kV cable trenching

 

EMSD projects

Contract No.

Project Title

Site Activities

1016EM10

Chilled Water Pipe Laying Works at North Apron Area for District Cooling System at Kai Tak Development

Trail Pit Excavation

1017EM10

Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak Development

1)    Construction of Site Offices

2)    Hoarding Erection

3)    Ground Investigation Works

4)    Trial Trenches Excavation

5)    Preliminary Works for Site Set-up

6)    Predrilling Works

 

List of Temporary Government Land Allocations (TGLAs)

TGLA No.

Name of Occupants

Site Activities

GLA-TNK 1591

CE/LW, Civil Engineering & Development Department

Works area for maintenance of equipments and storage

GLA-TNK 1578

CEO, Civil Engineering & Development Department

Depot area

GLA-TNK 1456

CGE/LPM3, Civil Engineering and Development Department

Works area for maintenance of equipments and storage

GLA-TNK 1525

Civil Engineering & Development Department

Engineer¡¦s Office and Contractor¡¦s Depot

GLA-TNK 1580

PM(K), Civil Engineering & Development Department

Works area for maintenance of equipments and storage

GLA-TNK 1646

GEO, Civil Engineering and Development Department

Stockpiling of excavated and construction materials

GLA-TNK 1581

PM(K), Civil Engineering & Development Department

Housekeeping of Ex GFS Building

GLA-TNK 1144

CE/PW, Civil Engineering and Development Department

Works Area for the Maintenance Term Contract for Piers and other Port Works

GLA-TNK 1226

CE/PW, Civil Engineering and Development Department

GLA-TNK 1636

Drainage Services Department

Works completed

GLA-TNK 1560

Slope Maintenance Section, Lands Department

Depot area

GLA-TNK 1177

Electrical and Mechanical Services Department

Vehicle maintenance depot

GLA-TNK 1338

Highways Department

Contractor¡¦s Maintenance Depot

GLA-TNK 1713

Highways Department

Storage

GLA-TNK 1709

Water Supplies Department

Works area for maintenance of equipments and storage

GLA-TNK 1608

Transport Department

1) Electronic equipment and system testing

2) Storage of equipment

GLA-TNK 1760

Drainage Services Department

Site office and storage area

GLA-TNK 1568

Fire Services Department

Driving training ground

GLA-TNK 1360

HK Police Force

Storage of police water barriers and metal gates

GLA-TNK 1334

Water Supplies Department

No major site activities (Project substantially completed)

GLA-TNK 1191&1542

Hong Kong Observatory

Automatic weather station

 

List of Short Term Tenancy (STT)

STT No.

Name of Occupants

Site Activities

KX2688

Goldway Parking Ltd.

Car-park

KX2345

CLP Power Hong Kong Limited

Storage of construction materials and plant equipments

KX2662

Hong Kong Cricket Association

Operation of Hong Kong Cricket Association

KX2628

Moral Well International Enterprise Limited

Car-park

KX2552

Era International Investment Limited

Car-park

KX2629

Graceful Ocean Development Limited

Car-park

KX2261

Hong Kong Aviation Club Ltd.

Training for air traffic controllers

KX2574

Future Chinese Limited

Car-park

KX2575

Nanjing Limited

Car-park

KX2117

Skyhill Resources Ltd.

Storage of building materials

KX2109

Multi-Light Limited

1) Concrete production

2) Storage of building materials

KX2675

Wang Lee Building Materials Trading Ltd.

Operation of business in the recovery and recycling

KX2676

Ga Shing Transport Co.

Operation of business in the recovery and recycling

KX2677

Chuen Kee Metal Trading Co Ltd.

Operation of business in the recovery and recycling

KX2678

Kin Xun Environment Recycle Ltd

Operation of business in the recovery and recycling

KX2569

Sureguard Logistics Limited

Open storage of goods and dangerous goods

KX2641

Citybus Limited

Parking of buses

KX2642

Goldway Parking Ltd.

Car-park

KX2616

CLP Power Hong Kong Limited

The area has been reinstated and handed over from CLP to DLO on 30 September 2010

 


1.9              The construction programme showing the inter-relationship with environmental protection/mitigation measures are presented in Table 1.3. 

Table 1.3    Construction Programme Showing the Inter-Relationship with Environmental Protection/Mitigation Measures

Construction Works

Major Environmental Impact

Control Measures

 

 

 

 

 

 

 

 

As mentioned in Table 1.2

Noise, dust impact, water quality and waste generation

 

Sufficient watering of the works site with active dust emitting activities

Properly cover the stockpiles

On-site waste sorting and implementation of trip ticket system

Appropriate desilting/sedimentation devices provided on site for treatment before discharge

Use of quiet plant and well-maintained construction plant

Provide movable noise barrier

Provide sufficient mitigation measures as recommended in Approved EIA Report/Lease requirement

Summary of EM&A Requirements

 

1.10          The EM&A programme requires construction noise monitoring, air quality monitoring, landscape and visual monitoring and environmental site audit.  The EM&A requirements for each parameter are described in the following sections, including:

 

¡P          All monitoring parameters;

¡P          Action and Limit levels for all environmental parameters;

¡P          Event Action Plans;

¡P          Environmental mitigation measures, as recommended in the Schedule 3 EIA Report; and

¡P          Environmental requirements in contract documents under Contract No. KLN/2010/04.

 

1.11          The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 6 of this report.

 

1.12          This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the required monitoring parameters, namely air quality and noise levels and audit works for the Project in April 2011.